Projects / 11kV Substation & Main Switchgear Modernization
CASE STUDY // ELECTRICALPrecision Automotive Foundry24,000 m² manufacturing plant

11kV Substation & Main Switchgear Modernization

11kV substation and MCC main switchboard replacement
FIELD RECORD // INDUSTRIAL ELECTRICAL & SWITCHGEAR

Engineering Performance Metrics & Delivery Parameters

Switchgear Rating3,200A 65kA 1s
Cable Terminated1,420 metres
Turnaround Window44 / 48 hrs
Lost Time Injuries0 LTI
FIGURE 1.0 // AS-BUILT SCHEMATICVerified by Lead Discipline Engineer
SCHEMATIC // 11kV SUBSTATION & LV DISTRIBUTIONDWG-E-8841
11kV INCOMING BUSBARVCBTX-01 1500kVA415V 3-PHASE 4-WIRE BUSBAR (3200A)ATS / GEN

The Technical Brief

Replace an obsolete 1994 main low-voltage distribution board and integrate automated bus-tie breaker synchronization with on-site 1,500kVA emergency generator sets.

Site & Operating Constraints

The foundry runs induction melt furnaces that cannot experience uncontrolled cooling. All primary feeder de-energization, cable pulling, termination, and primary injection testing had to conclude within a single 48-hour window without extension.

Execution Methodology & Works Delivered

  • Prefabricated and tested a 3,200A Form 4b Type 2 switchboard at our workshop prior to delivery
  • Deployed 16 certified cable jointers and electrical fitters working dual 12-hour shifts
  • Re-routed 36 runs of 4-core 240mm² XLPE/SWA cables onto newly installed heavy-duty steel ladder racking
  • Performed dielectric insulation, contact resistance, and relay secondary injection calibration tests
  • Witnessed power-up with the local utility distribution authority 4 hours ahead of schedule

Verified Outcome

Full re-energization achieved in 44 hours against the 48-hour limit. Arc-flash boundary ratings lowered to Category 2 across all panels, with zero safety incidents logged.

Discuss Similar Facility Scope

If your plant requires similar switchgear cutover, refrigeration overhaul, or cleanroom installation, speak directly with our team.

Discuss via WhatsAppSubmit Detailed RFQ

Job Summary

Total Duration7 weeks offsite staging, 44 hours live switchover
Downtime Allocation48-hour scheduled national holiday outage