Projects / High-Bay Structural Mezzanine & Crane Runway
CASE STUDY // STRUCTURALFMCG Regional Logistics Distribution Hub45,000 m² automated facility

High-Bay Structural Mezzanine & Crane Runway

Heavy structural steel fabrication and mezzanine erection
FIELD RECORD // STRUCTURAL STEEL FABRICATION & CERTIFIED WELDING

Engineering Performance Metrics & Delivery Parameters

Fabricated Steel65.4 tonnes
Design Live Load7.5 kN/m²
Night Shifts28 shifts
Lost Shift Count0 hours
FIGURE 1.0 // AS-BUILT SCHEMATICVerified by Lead Discipline Engineer
STRUCTURAL CAD // CONNECTION DETAILDETAIL-STR-401
UC 254x254x73UB 406x178x676x M24 GRADE 8.8 BOLTS (TORQUED 450Nm)

The Technical Brief

Fabricate, deliver, and erect a 65-tonne structural steel sorting mezzanine and 5-tonne overhead hoist runway beam above active ground sorting lines.

Site & Operating Constraints

Zero disruption permitted to daytime automated package sortation. All crane lifts and bolted connections had to be executed, torqued, and cleared before 05:00 each morning.

Execution Methodology & Works Delivered

  • Fabricated S355JR structural columns, beams, and cold-formed joists in our Peliyagoda fabrication yard
  • Utilized mobile spider cranes and electric boom lifts fitted with non-marking tires for indoor night erection
  • Fastened all connections with Grade 8.8 structural bolts tightened to calibrated torque logs
  • Installed safety interlocked swing gates, kickplates, and industrial mesh decking
  • Performed ultrasonic weld testing (UT) on all moment splice joints

Verified Outcome

Completed on schedule with zero daytime fulfillment interruptions and 100% structural engineer sign-off upon load deflection testing.

Discuss Similar Facility Scope

If your plant requires similar switchgear cutover, refrigeration overhaul, or cleanroom installation, speak directly with our team.

Discuss via WhatsAppSubmit Detailed RFQ

Job Summary

Total Duration8 weeks total duration
Downtime AllocationNight-shift access windows (22:00–05:00) only