Projects / High-Pressure Steam Ring Main & Condensate Overhaul
CASE STUDY // PIPING•Industrial Polymer Chemical Plant•12,000 m² chemical synthesis plant
High-Pressure Steam Ring Main & Condensate Overhaul

FIELD RECORD // MECHANICAL PIPING, STEAM & PUMPS
Engineering Performance Metrics & Delivery Parameters
Design Pressure12 bar gauge
Hydro Test18 bar hold
Weld Rejection0% RT fail
Monthly Savings$3,800 steam
FIGURE 1.0 // AS-BUILT SCHEMATICVerified by Lead Discipline Engineer
STRUCTURAL CAD // CONNECTION DETAILDETAIL-STR-401
The Technical Brief
Replace 320 metres of leaking 6-inch 12-bar saturated steam main piping, upgrade pressure reducing stations, and install thermodynamic steam trap stations with automated condensate monitoring.
Site & Operating Constraints
Steam header supplies reactors holding temperature-sensitive chemical batches. Cutover window was tied strictly to boiler statutory cool-down cycles.
Execution Methodology & Works Delivered
- Prefabricated 48 flanged spool pieces in ASTM A106 Grade B seamless carbon steel
- Certified 6G TIG root and SMAW cap welders executed 74 tie-in welds on site
- Conducted 100% radiographic testing (RT) and hydro-tested the assembly to 18 bar (1.5x design)
- Installed pre-formed mineral wool insulation with heavy-gauge embossed aluminum cladding
- Calibrated Spirax Sarco PRV stations and commissioned steam traps with acoustic leak monitors
Verified Outcome
Eliminated $3,800 monthly steam loss, stabilized process reactor supply pressures to within ±0.1 bar, and received Labour Department statutory boiler inspector certification.
Discuss Similar Facility Scope
If your plant requires similar switchgear cutover, refrigeration overhaul, or cleanroom installation, speak directly with our team.
Discuss via WhatsAppSubmit Detailed RFQJob Summary
Industry SectorManufacturing Plants & Heavy Processing
Core ServiceMechanical Piping, Steam & Pumps
Total Duration4 weeks prefabrication, 68 hours on-site cutover
Downtime Allocation72-hour annual boiler inspection window