Projects / High-Pressure Steam Ring Main & Condensate Overhaul
CASE STUDY // PIPINGIndustrial Polymer Chemical Plant12,000 m² chemical synthesis plant

High-Pressure Steam Ring Main & Condensate Overhaul

High pressure steam ring main and pump manifold installation
FIELD RECORD // MECHANICAL PIPING, STEAM & PUMPS

Engineering Performance Metrics & Delivery Parameters

Design Pressure12 bar gauge
Hydro Test18 bar hold
Weld Rejection0% RT fail
Monthly Savings$3,800 steam
FIGURE 1.0 // AS-BUILT SCHEMATICVerified by Lead Discipline Engineer
STRUCTURAL CAD // CONNECTION DETAILDETAIL-STR-401
UC 254x254x73UB 406x178x676x M24 GRADE 8.8 BOLTS (TORQUED 450Nm)

The Technical Brief

Replace 320 metres of leaking 6-inch 12-bar saturated steam main piping, upgrade pressure reducing stations, and install thermodynamic steam trap stations with automated condensate monitoring.

Site & Operating Constraints

Steam header supplies reactors holding temperature-sensitive chemical batches. Cutover window was tied strictly to boiler statutory cool-down cycles.

Execution Methodology & Works Delivered

  • Prefabricated 48 flanged spool pieces in ASTM A106 Grade B seamless carbon steel
  • Certified 6G TIG root and SMAW cap welders executed 74 tie-in welds on site
  • Conducted 100% radiographic testing (RT) and hydro-tested the assembly to 18 bar (1.5x design)
  • Installed pre-formed mineral wool insulation with heavy-gauge embossed aluminum cladding
  • Calibrated Spirax Sarco PRV stations and commissioned steam traps with acoustic leak monitors

Verified Outcome

Eliminated $3,800 monthly steam loss, stabilized process reactor supply pressures to within ±0.1 bar, and received Labour Department statutory boiler inspector certification.

Discuss Similar Facility Scope

If your plant requires similar switchgear cutover, refrigeration overhaul, or cleanroom installation, speak directly with our team.

Discuss via WhatsAppSubmit Detailed RFQ

Job Summary

Total Duration4 weeks prefabrication, 68 hours on-site cutover
Downtime Allocation72-hour annual boiler inspection window